No slip-ups here!
At the newly named Centenary Place, carborundum anti-slip strips have been added to the steps. Carborundum is a compound of silicon and carbon that is used as an abrasive. It has a gritty texture that is similar to sandpaper, making it effective at providing a safer surface, particularly in wet conditions. Also at Centenary Place, timber cladding has been installed on the new terraced seating.
A great leveller
The durable Yorkstone sandstone within the Naval War Memorial walkway is now installed, meaning that the previous stepped access is no more and you will soon enjoy level access between the memorial and the promenade! Yorkstone (from Yorkshire) gives an attractive and accessible entrance to the memorial – a most fitting material for this important historical site. The photo shows the special granite blocks on the road in front of the Naval War Memorial which are now 50% complete.
‘Kerb’ your enthusiasm
Kerb lines continue to be installed to provide safe boundaries between the two-way cycle lane and the footpaths on both sides of the lane. Another safety feature here is a new crossing point near Blue Reef Aquarium. We look forward to this area being well-used by cyclists and pedestrians alike when it opens in spring 2026. Stay tuned for details…
Creating a diversion…
From February, you’ll notice us preparing the area between Speakers’ Corner and South Parade Pier for the construction of new sea defences. The main work and promenade closure are due to begin on 2 March 2026. Work is expected to be complete by May 2027.
During this period, a short section of Clarence Esplanade at The Dell will be closed, with a walking and cycling diversion. There will also be traffic management to keep vehicles at a safe distance from the work, but the road will stay open in both directions.