Weekly update – 29 January 2021

One month into 2021 and great progress is being made on frontage 1. This week we continued sheet piling for the front row of piles from the Saluting Platform, heading west to the Spur Redoubt. This will continue next week.

Tuesday 26 January saw us marking Australia Day, making our Aussie team member feel right at home!

Back on site, we levelled and maintained the west and east working platforms for crane and plant access, and formed working access for the concrete works on the east side.

Concrete forms and cast concrete foundations have been set up in preparation for the concrete beam between the steel sheet piles and the proposed rock revetment. This will continue next week.