Looking bronzed
All monuments along Frontage 3 (Southsea Common) are now back in place and are looking great, thanks to having their intricate bronze elements fitted. Yorkstone paving has been installed around them all which adds to their visual appeal. When you walk along the new area later this year, you’ll notice that the monuments are now located along the centre of the promenade, making a memorial trail for all to enjoy.
Playing up
Children visiting Frontage 3 (Southsea Common) when it opens in spring (stay tuned for details) will be delighted at the new play features that have been installed at Centenary Place. The pirate ship takes pride of place, with other wooden play features that are sure to provide lots of fun and activity. The photo shows the first layer of soft surfacing (black). Still to be added on top of this black layer is a more colourful layer in a pattern.
Surface area
Despite the wet weather, we’ve made great progress on the surfacing around the Naval War Memorial. The granite blocks on the road in front of the memorial are now 90% complete. We’re also getting prepared for placing the final layer of surfacing to the highway, cycle lane and buffer strip. This is due to start next week.
Work update – closures and diversions
From 16-27 February we will be conducting enabling works in front of the Co-op on South Parade. Enabling works are the first step in most construction projects before works begin. This will require the eastbound traffic lane narrowing; temporary shortening of the Co-Op layby; and partial closure of the footpath. The temporary works will re-align the kerbs and bollards at the end of the layby to make it easier for traffic to pull out of the layby. The work will be during the daytime only.
Please also be reminded that the promenade between Speakers’ Corner and South Parade Pier will be closing from March 2026 until May 2027 as we revamp the area as part of our flood defence works.