Update from the scheme – 18 July 2026

18.07.26

Work on Frontage 5 East is continuing at pace, with more precast concrete units being installed between South Parade Pier and Speakers’ Corner. The team is currently averaging around six units a day in good weather and has now made significant progress towards its target of 349 units.

Elsewhere, the capping beam in front of the seating area next to South Parade Pier has been completed, and new ducting is being installed to provide power to both the historic lighting columns and new lighting within the planting terraces.

Residents are also invited to meet the project team at a roadshow drop-in event on the promenade near Speakers’ Corner on Thursday 20 August, from 10am to 1pm.

Read the full bulletin: Southsea Coastal Scheme update