Forecast marine works 11-20 August 2022

Please see the latest forecast for upcoming marine works in the link below.

SF4 Week plan Week 32-33

Please note that the work schedule is subject to change and will only proceed WP AGW (weather permitting; all going well).

Our rock work is for completion by the end of September 2022. We appreciate your patience over this time and, as always, we will monitor noise throughout the works and try to minimise disturbance as much as possible.

Note: As part of our Planning Permission, there is a condition that marine works such as rock placement and delivery are not constrained to normal working hours of 07:00 to 19:00 Monday to Friday and can be scheduled 24/7. In addition, due to the need to work around tidal conditions, we have a condition in our Contract Scope that permits marine works on a 24/7 basis: Marine works, that are tidally restricted such as rock deliveries and placement, are exempt from the working hours.