News from the scheme – 22 May 2026

22.05.26

A quick update….

From next week, we will be putting a brief news update here on the website on a Monday, after the e-bulletin goes out on a Saturday.

So, make sure you sign up for the e-bulletin to be the first in the know with everything that’s going on! Sign up here.

Westside story!

tiered units

South Parade Pier to Speakers’ Corner (Frontage 5 East) is coming along nicely this week. We have started installing the precast units at the Western end of site now starting with the lower wall of the tiered roadside planters (as pictured).

We have also started installing the stepped revetments from the Western end – these will connect the new height of the promenade to the beach.

Getting our ducts in a row…

ducts being laid

Also on Frontage 5 East at the Eastern end, we have installed ducts. These are for the electrical connections for all of the street lights and other electrical services to be able to run through the new frontage. They are pictured here ready for backfilling (covering up) which has now been done.

A true asset!

EA asset team

This week we had a visit from the Environment Agency Asset Team Leaders as part of their bi-annual Asset Performance Team Leader Conference.

We presented the work we have been doing at Southsea Coastal Scheme and gave a tour of our completed frontages.

Strong feedback for new Southsea seafront…

southsea prom

The first feedback on the newly opened Frontage 3 seafront is in, and it’s overwhelmingly positive.

Out of nearly 600 responses, 93% said they’re happy with the changes, and 97% rated the quality as good or very good.

People particularly like the fresh new look, along with the seating, shelters and historic features. And it’s already making a difference, as almost nine in ten said it encourages them to visit more often.

Thanks to everyone who shared their views your feedback is helping shape the next stages of the Southsea Coastal Scheme.